Thursday, August 13, 2009

Here is our guy...the builder of kitchen cabinets. A man in his glory.


Hello all, We are now digging the ditches for the lines for water, electricity, cable ,etc.


Gary and crew are starting the stick framing today if they can get throught the 96 degree weather. It is all exciting!


Sunday, August 9, 2009

Waiting...

Well, we are on hold for now. We expect the pouring of the garage pad and workshop pad by Tuesday. We can put our handprints in the wet cement too. Ha!
We will send pics soon as progress is made. Thanks for joining us.

Sunday, August 2, 2009

This is the crew:
Gary, our contractor, Walt, Dave (Caitlin's guy), Frank and Brian.






The "boss" showing her husband where the furniture goes.


The garage is in the front to the left of our courtyard. It will need some fill for a concrete pad.




Facing the right side of house down the hillside.You can see 3-4 defined rectangular forms for the pour. Closest room is our bedroom and then the Great room then a den/bedroom.
This is the front of the house where we will drive up to the courtyard(see the opening).

Kneier House Building

Hope our photos come through okay. Let us know if you can not find them.
All is quiet as it is Sunday and the crew is resting.